
Building 4, Croxley Business Park, Watford
Strip-out, refurbishment and CAT-A fit-out works to commercial Suites 5 & 6 of Building 4 at Croxley Park.
PROJECT OVERVIEW
Client: Watford Borough Council
Contract Value: £750,000
Duration: 14 Weeks
Contract Type: JCT 2016 with Design
We completed a strip-out, refurbishment and CAT-A fit-out works to commercial Suites 5&6 at a fully occupied and operational Croxley Business Park for Watford Borough Council, alongside project partners, Workman LLP.
Key Points:
Strip-out, refurbishment and fit-out of Suites 5&6
CAT-A fit-out, including fully exposed MEP services
Exposed existing steelwork with feature acoustic baffles
New raised access floor throughout
Full decoration and finishes
Re-spraying of all existing window frames and exposed soffit panels
Works carried out in a fully occupied building; noisy works were agreed and carried out ‘Out of Hours’ to minimise disruption to building users.


