Dukes Park Industrial Estate, Chelmsford

Strip-out and refurbishment work to two industrial units situated on the fully operational Dukes Park Industrial Estate.

PROJECT OVERVIEW

Client: BAE Systems Pension Fund Trustees
Contract Value: £900,000
Duration: 25 weeks
Contract Type: JCT Intermediate with CDPs

Key Features:

  • Strip-out of asbestos, fixtures and fittings and removal of floor slab

  • Application of Epoxy self-levelling resin with Latex, vinyl and Flocrete Flowcoat floor finishes to create a smooth and durable surface

  • Extensive MEP services installation and upgrades

  • Roof works comprised repair, installation of roof lights, bird netting, perimeter handrails and mobile elevating work platform system

  • Construction of new block work party walls which required close and regular liaison with neighbouring tenants

  • New windows and doors, along with main access roller shutters to both units

  • Structural steel work, installation of glazed canopy and external works - paving bollards, perimeter fencing and access gates