Guy’s & St Thomas’ Hospitals

Multiple refurbishment and M&E services upgrade schemes across both hospitals through our Kings Health Partnership Framework Agreement.

PROJECT OVERVIEW

Client: Guy’s & St Thomas’ NHS Foundation Trust
Contract Value: Projects up to £2,500,000
Duration: Three-year framework
Contract Type: NEC Engineering & Construction Short Contract

PROJECT OVERVIEW

Many sites were fully occupied, requiring high levels of health and safety and segregation. We took considerable precautions to comply with the clinical environment restrictions to keep noise, dust and vibration to a minimum to avoid disturbing patients and staff members, or specialist equipment.

Key Projects:

  • Pharmacy, St Thomas’ Hospital: Complete refurbishment and installation of new state-of-the-art dispensary robot.

    • Contract Value: £2,500,000

    • Contract Duration: 25 weeks

  • Paediatric Long-Term Ventilation, St Thomas’ Hospital: Refurbishment to ward that provides specialist care and services to children.

    • Contract Value: £1,200,000

    • Contract Duration: 25 weeks

  • Pharmacy Product Store, Guy’s Hospital: Refurbishment of storeroom for medicines, tablets and prescriptions.

    • Contract Value: £300,000

    • Contract Duration: 14 weeks

  • Dentistry, Guy’s Hospital: Refurbishment of Communications Tower level 17.

    • Contract Value: £175,000

    • Contract Duration: 10 weeks