Heathside Junior School, Weybridge
Demolition of existing classroom building block and construction of the new teaching block at Heathside School.
PROJECT OVERVIEW
Client: Elmway Learning Trust/Department for Education
Contract Value: £2,000,000
Duration: 51 Weeks
Contract Type: JCT Design & Build 2016
The demolition of an existing classroom building block and construction of the new teaching block at Heathside School, for Elmway Learning Trust under the Department for Education Framework Agreement.
Key Points:
Demolition of existing school building
Construction of the new build classroom block consisting of six classrooms, toilets and staff office spaces
Upgrade works to the external area, including new tarmac, walkways and improved access
Greenery planted at the building entrance and around the new walkways
Large windows throughout the building to create a large, bright and spacious learning space
Toilets installed with a unisex hand washing space; two sets of student lockers fitted in the corridors
Staff office spaces were created at either end of the building for general administration, including the installation of new computers
Works were delivered 2 weeks ahead of schedule
Key Challenges:
Working within a ‘live environment’ for most of the project
Restrictions to works were put in place between student drop off and pick up times, meaning deliveries and works had to be carefully planned around this
Noisy works were approved beforehand to try to minimise disruption to the school