John Ruskin College, Croydon

Construction of a new build Construction Skills Centre for John Ruskin College, within the boundary of the existing college.

PROJECT OVERVIEW

Client: John Ruskin College
Contract Value: £1,500,000
Duration: 47 Weeks
Contract Type: JCT D&B 2016

PROJECT OVERVIEW

Key Points:

  • Two-stage Design and Build of Construction Skills Centre with Mezzanine level

  • Warehouse-style centre with two large work areas - one on the ground level and a second workspace on the mezzanine level

  • Simple, open and minimal workspace design with exposed features

  • Toilets on both levels

  • Plant room installation

  • Office fitted on the ground floor

  • External cycle store

Key Challenges:

  • The second stage of the works was approved once the project had begun - The original scheme was for a single-storey building only, but the client decided to add a storey Mezzanine level 8 weeks into the project

  • Construction had to be paused for the redesign to take place - work then recommenced once the design and planning had been approved

  • Two-stage D&B project - coordination and communication between the client and design team were key throughout the programme

  • Live Environment - for the most part, the college was open as normal and noise and disruption had to be kept to a minimum

  • External work as a result of the live environment was difficult at times as the car park had to be kept clear for the staff and students to use; deliveries had to be carefully planned and timed