Extensive refurbishment works to the complete external envelope of the College’s 5-storey Main Teaching Block.
PROJECT OVERVIEW
Client: Barnet & Southgate College
Contract Value: £2,000,000
Duration: 50 Weeks
Contract Type: JCT Standard with CDP
PROJECT OVERVIEW
As an approved construction partner for Barnet & Southgate College, our contracting team delivered extensive refurbishment works to the complete external envelope of the College’s 5-storey Main Teaching Block at their occupied Southgate campus
Key Points:
Erection of full-height scaffold system with Tufcoat wrap and hoist provision
Removal of existing curtain walling, render, Crittall windows and asbestos
Installation of Technal aluminium cladding and window panels, euroSol vertical box fin system, and Brise-Solel to the south-facing elevation
Application of Sto render, concrete repairs and new signage
Coordination of M&E services and links to building interface
Internal refurbishment to ‘make good’ following installation
Key Challenges:
Delivering in a Live Campus Environment - Health and safety was a top priority, and we worked closely with key stakeholders, facilities management team and end-users to carefully plan and reduce, wherever possible, our interface with the students, staff and members of the public.
Complete Segregation - The site boundary of the Block was fully secured whilst the campus remained live and operational, and we erected a full-height scaffold with a protective Tufcoat wrap and walkways to access the external envelope.