Panerai
Internal fit-out to Basement and Ground floors forming a new flagship store in New Bond Street.
PROJECT OVERVIEW
Client: Loewe Hermanos UK Ltd
Contract Value: £3,000,000
Duration: 57 Weeks
Contract Type: JCT Standard with CDP
PROJECT OVERVIEW
Internal fit-out and external shop front refurbishment works to the Ground floor and Basement forming the new flagship store for Panerai
Key Points:
Minor strip-out, removal of a mezzanine floor and specialist damp proofing application to Basement
New partitions, Polished plaster ceilings and walls
Formation of an architectural staircase with integrated metalworks mullions and fascias
Bespoke joinery elements including display units, showcases and ‘workstation’
Hardwood, natural stone and decorative vinyl flooring
Installation of new M&E services; smoke cloak, data, security, fire alarm and lighting features
New doors and ironmongery installed throughout along with staff kitchen and toilets
Full high-end decoration throughout
New glazed shop front with security features, brand signage and fixed flag pole