PROJECT OVERVIEW
Client: DFE/Oxfordshire County Council
Contract Value: £3,100,000
Duration: 61 Weeks
Contract Type: JCT Design & Build 2016
Delivered over five phases to allow the school to remain operational, we delivered a new build block and refurbishment of the existing facilities to allow St Blaise Primary School to double their capacity.
Phase 1: Construction of Temporary Access Road
Phase 2: Hard Play Surface & Car Park
Phase 3: Kitchen Extension and Fit-Out
Phase 4: New Classroom Block and External Areas
Phase 5: Main Entrance Extension and Internal Refurbishments Works
The new build block houses four classrooms, along with a staff room, library corner, toilets and shower/washroom. Externally, a new astroturf/sports pitch was installed along with new bike sheds. We proposed an alternative boiler system/radiator for the new building to the client, which resulted in a cost saving of £10k.
Throughout the project, we delivered 56 apprenticeship weeks for a Trainee Surveyor, who we went on to employ after the project was completed. Despite the restrictions of COVID-19, we organised a site visit for all of the students at the school with a Q&A session about their new building, construction safety and our delivery process. We created a temporary access road to the Bowls Club (adjacent to the school) to access our site compound; we tidied up the access road, cleared out all the shrubbery and left this in place for the Bowls Club to utilise going forward.