St Joseph's Catholic School, Leyton

Phased refurbishment, asbestos removal and roofing works to fully occupied and operational infant school.

PROJECT OVERVIEW

Client: London Borough of Waltham Forest
Contract Value: £2,500,000
Duration: 59 Weeks
Contract Type: JCT Intermediate with CDP

Key Points:

  • Works implemented in five phases

  • Procured through Barking and Dagenham’s Contractor Framework

  • Works to front entrance, main reception, six classrooms, nursery and main assembly hall

  • Enabling works and provision of new temporary mobile classrooms including full services

  • Strip-out and asbestos removal

  • Single-storey extension to form a new front entrance

  • Replacement and installation of aluminium works

  • Full reroofing works to main school buildings

  • Internal decorations, new floor coverings, ceiling works and incorporated ventilation units

  • M&E services including feature lighting, new plant room and boiler installation

  • Works to playground with new DDA access ramps

  • Complete within the project timeframe